Main airport works

The main airport works program will be procured in packages.

The first package ‘Bulk Earthworks Airside Civil Works’ covers earthworks, drainage and utilities, together with airside pavements and is broken down into three sub-packages:

  • Bulk Earthworks Package A;
  • Bulk Earthworks Package B; and
  • Pavements Package.

‘Bulk Earthworks Package A’ will cover the bulk earthworks, relocation of utilities, and decontamination to cover the Northern sector of the Stage 1 site. This sub-package of works will also play a key role in establishing the mastergrading for the site. The Expression of Interest for this package has been released. It is expected that a preferred tenderer will be contracted in the second half of 2019 and that works will commence later that year.

‘Bulk Earthworks Package B’ includes the bulk earthworks, relocation of utilities, and decontamination to cover the Southern sector of the Stage 1 site. This package of works is expected to be awarded in mid-2020. 

‘Pavements Package’ covers all of the airside civils within the Stage 1 site and is expected to be awarded in mid-2021.

The second major package will be the terminal building and associated airside and landside interface works.

The third package will cover the landside roads, carparks and associated works.

A number of smaller specialty works and services packages for services such as IT, security and baggage handling systems will be issued for tender separately and integrate with the main works.
The successful tenderer/s will need to meet the environmental, safety, and security requirements under the Airport Plan, Environmental Impact Statement and functional specifications.