Enabling activities are the physical activities to be undertaken at the site, primarily before the main airport works construction program begins. Enabling activities cover five packages of work, each with a separate tendering process and delivery timeframe.

  • Geotechnical investigations and bedrock analysis including over 100 additional boreholes in the runway and taxiway areas.
  • Land survey (including cadastral surveying to map the site and feature surveys), services locations and aerial photography.
  • A 12-month program of air and noise monitoring both before and during construction works.
  • Relocation of a 330-kilovolt high-voltage TransGrid transmission line from overhead to an underground cable route.
  • Early earthworks to move approximately 1 million cubic metres of earth, and potential stockpiling for on-site fill materials.

Current tenders

  • Independent Certifier Services: CLOSED (3 APRIL 2019)
  • Terminal Precinct Architect and Interior Design Services: CLOSED (21 FEBRUARY 2019)
  • Visitors Centre & Office Accommodation Works: CLOSED (4 AUGUST 2018)
  • Bulk Earthworks and Airside Civil Works - Registration of Interest (Bulk Earthworks Package A) CLOSED (24 AUGUST 2018)
  • Airport Planning Services: CLOSED (2 JULY 2018)
  • Technical Services Panel—Engineering Services: CLOSED (21 May 2018)
  • Technical Services Panel—Quantity Surveying Services: CLOSED (21 May 2018)
  • Early Earthworks—Registration of Interest: CLOSED (7 March 2018)
  • Delivery Partner—Expression of Interest: CLOSED (28 February 2018)
  • Project Manager (Definition)—Expression of Interest: CLOSED (28 February 2018)

Contracts awarded

  • The contract for Baggage Handling Concept Design was awarded to AV logic on the 26 February 2019.
  • The contract for the Airport Planner was awarded to Arup on the 12 November 2018.
  • The contract for the Visitor Centre and Office Accommodation was awarded on 26 October 2018 to Watpac Construction Pty Ltd.
  • The contract for Early Earthworks was awarded on 29 June 2018 to CPB Contractors & Lendlease Engineering Joint Venture

  • The contract for the Delivery Partner and Project Manager Definition was awarded on 29 June 2018 to Bechtel Australia

     

  • The contract for Land Survey Services was awarded on 15 December 2017 to Veris.
  • The contract for Geotechnical Investigation Services was awarded on 22 November 2017 to JK Geotechnics.